The Asv Pioneer has arrived at Giglio Island and is now positioned near the wreck of the Costa Concordia. Owned by Scottish group Ferguson Zoom and chartered for six months by the Titan Micoperi Consortium tasked with removing the Concordia, the platform will provide support for work to create a false sea bottom using special grout bags.
The 60 double cabins in the platform will provide accommodation for the team of divers who will work day and night to complete work on schedule. The platform’s deck area will also be used for some of the equipment needed to produce the cement mortar and assemble the removable bags that will be positioned in the dip in the sea bottom at the centre of the wreck. The Pioneer, built in 2007 by Nantong Tongcheng Ship Manufacturing and purchased by Ferguson in 2009, was converted in Glasgow by the new owner and is now able to accommodate a total of 220 people, while the 1,100 sq m deck can be used for equipment weighing up to 15 tons per square meter.
The Parbuckling Project
Concordia wreck removal project informative website
Flash news :
- 19/05/2013 Drillings for hole number 18 started today -
- 05/05/2013 Grout bags filling activity is continuing, with a total of about 54% -
- 05/05/2013 Welding of sponson P10 and P11 bumpers in progress -
- 22/04/2013 438 people currently working at the Giglio's yard -
- 22/04/2013 About 50% of grout bags filling activity has been completed -
- 22/04/2013 Last analysis have reported positive feedback on the Giglio's water quality -
- 30/03/2013 First large platform n° 1 installed and grouted -
- 11/03/2013 Positioning of platform 4 completed -
- 24/02/2013 Anchor Blocks n° 9, 10, 11 grouting completed -
- 24/02/2013 Anchor Blocks n° 6, 7 and 12 completed and installed -
- 10/02/2013 2 small platforms installed (numbers 5 and 6) -
Overall Project progress:
58%
| Anchor Blocks | Drilling Holes | Sponsons |
| 11 installed | 16 completed | 2 installed |
| 1 to be installed | 4 to be done | 13 to be installed |
| -- | 1 in progress | -- |
Vessels and crafts on site: 27
Estimated number of employee on site: 467 persons
Search
Register
PONTOON PIONEER ARRIVED AT GIGLIO ISLAND
22/10/2012 - Isola del Giglio