The Parbuckling Project
Concordia wreck removal project informative website
Flash news :
- 15/06/2013 Observatory communicates positive data on sea water quality at Giglio -
- 13/06/2013 Drilling activity for last subsea platform installation completed -
- 07/06/2013 About 64,8% of grout bags filling activity has been completed -
- 03/06/2013 Platform n. 2 installed, the fifth of 6 -
- 05/05/2013 Welding of sponson P10 and P11 bumpers in progress -
- 05/05/2013 Grout bags filling activity is continuing, with a total of about 54% -
- 22/04/2013 Last analysis have reported positive feedback on the Giglio's water quality -
- 30/03/2013 First large platform n° 1 installed and grouted -
- 11/03/2013 Positioning of platform 4 completed -
- 24/02/2013 Anchor Blocks n° 9, 10, 11 grouting completed -
- 24/02/2013 Anchor Blocks n° 6, 7 and 12 completed and installed -
- 10/02/2013 2 small platforms installed (numbers 5 and 6) -
Overall Project progress:
62,5%
| Anchor Blocks | Drilling Holes | Sponsons |
| 11 installed | 21 completed | 2 installed |
| 0 to be installed | 0 to be done | 13 to be installed |
| -- | -- | -- |
Vessels and crafts on site: 25
Estimated number of workers on site: 474 persons
Search
Register
Media requests
In order to facilitate the regular prosecution of activities related to the removal project, willing to also guarantee an adequate support to media operators working at Giglio Island, we reccomend to fill the form below, specifying the purpose of your request (request for interviews, specific content requests). This will allow us to set up the best conditions possible. Contact this address for any further request