The Parbuckling Project
Concordia wreck removal project informative website
Flash news :
- 19/05/2013 Drillings for hole number 18 started today -
- 05/05/2013 Grout bags filling activity is continuing, with a total of about 54% -
- 05/05/2013 Welding of sponson P10 and P11 bumpers in progress -
- 22/04/2013 438 people currently working at the Giglio's yard -
- 22/04/2013 About 50% of grout bags filling activity has been completed -
- 22/04/2013 Last analysis have reported positive feedback on the Giglio's water quality -
- 30/03/2013 First large platform n° 1 installed and grouted -
- 11/03/2013 Positioning of platform 4 completed -
- 24/02/2013 Anchor Blocks n° 9, 10, 11 grouting completed -
- 24/02/2013 Anchor Blocks n° 6, 7 and 12 completed and installed -
- 10/02/2013 2 small platforms installed (numbers 5 and 6) -
Overall Project progress:
58%
| Anchor Blocks | Drilling Holes | Sponsons |
| 11 installed | 16 completed | 2 installed |
| 1 to be installed | 4 to be done | 13 to be installed |
| -- | 1 in progress | -- |