Flash news :

  • 19/05/2013 Drillings for hole number 18 started today     -
  • 05/05/2013 Grout bags filling activity is continuing, with a total of about 54%     -
  • 05/05/2013 Welding of sponson P10 and P11 bumpers in progress     -
  • 22/04/2013 438 people currently working at the Giglio's yard     -
  • 22/04/2013 About 50% of grout bags filling activity has been completed     -
  • 22/04/2013 Last analysis have reported positive feedback on the Giglio's water quality     -
  • 30/03/2013 First large platform n° 1 installed and grouted     -
  • 11/03/2013 Positioning of platform 4 completed     -
  • 24/02/2013 Anchor Blocks n° 9, 10, 11 grouting completed     -
  • 24/02/2013 Anchor Blocks n° 6, 7 and 12 completed and installed     -
  • 10/02/2013 2 small platforms installed (numbers 5 and 6)     -
 

Overall Project progress:

58%

Anchor Blocks Drilling Holes Sponsons
11 installed 16 completed 2 installed
1 to be installed 4 to be done 13 to be installed
 --  1 in progress  -- 

Vessels and crafts on site: 27

Estimated number of employee on site: 467 persons

 

 