Flash news :

  • 15/06/2013 Observatory communicates positive data on sea water quality at Giglio     -
  • 13/06/2013 Drilling activity for last subsea platform installation completed     -
  • 07/06/2013 About 64,8% of grout bags filling activity has been completed     -
  • 03/06/2013 Platform n. 2 installed, the fifth of 6     -
  • 05/05/2013 Welding of sponson P10 and P11 bumpers in progress     -
  • 05/05/2013 Grout bags filling activity is continuing, with a total of about 54%     -
  • 22/04/2013 Last analysis have reported positive feedback on the Giglio's water quality     -
  • 30/03/2013 First large platform n° 1 installed and grouted     -
  • 11/03/2013 Positioning of platform 4 completed     -
  • 24/02/2013 Anchor Blocks n° 9, 10, 11 grouting completed     -
  • 24/02/2013 Anchor Blocks n° 6, 7 and 12 completed and installed     -
  • 10/02/2013 2 small platforms installed (numbers 5 and 6)     -
 

Overall Project progress:

62,5%

Anchor Blocks Drilling Holes Sponsons
11 installed 21 completed 2 installed
0 to be installed 0 to be done 13 to be installed
 --   --   -- 

Vessels and crafts on site: 25

Estimated number of workers on site: 474 persons

 

 